|
The National Transmission Corp. said that the construction works
for the submarine cable component of the Cebu-Negros Interconnection
Uprating Project has already started last month and its completion
is expected in June next year.
TransCo said in its Feburary report that the project, aimed
to increase the carrying capacity of an existing submarine cable
from 100 to 200 megawatts, will also commence ground works for the
transmission line and substation components in April and will complete
construction on November 2007.
The report also said that the Negros-Panay Interconnection
Uprating Project, which will double the capacity of the existing
line to 200 megawatts, will be awarded to the winning contractor
this June. Its target completion is first quarter of 2008.
TransCo president Alan Ortiz said that these projects will
increase the reliability and stability of the Leyte-Cebu-Negros-Panay
grid and also optimize the use of indigenous power resources from
Leyte, the report said.
Last month, the TransCo also completed the laying of the submarine
cable for the 69-kilovolt Panay-Boracay Interconnection Project.
The 1.6-kilometer submarine cable was connected to the Caticlan
cable terminal station and to another in Manok-Manok, Boracay.
The P149-million power project is the first phase of the Small
Island Submarine Interconnection Development Program that will establish
a bi-directional electricity highway in Philippines' western corridor
and complete the Luzon-Visayas Transmission Loop.*NLG
back to top
|